Bergen gas engines and LNG, two familiar topics for Diesel International readers. In this case we have found a way to bring the two instances together. We propose what we received from Rolls-Royce Power Systems.

Bergen gas engines
Core equipment for the new gas-based power plant for the LNG terminal at India’s east coast will include three 9.6 MW gensets, based on the 20-cylinder Rolls-Royce Bergen B35:40 gas engines.

Bergen gas engines to Dhamra LNG Terminal

“Rolls-Royce has signed a contract with Dhamra LNG Terminal Pvt. Ltd. (DLTPL) for the complete Engineering, Procurement and Construction (EPC) delivery of a 29 MW gas-based power plant for an Indian LNG terminal. DLTPL is a joint venture between Indian multinational conglomerate Adani Group and French energy major Total S.A, located on the eastern coast of Odisha in India. The LNG terminal will function as a reception facility for import of LNG, where LNG tankers can directly unload cargo and converting the LNG gas from liquid state to gaseous state. The highly efficient power plant will meet the baseload capacity of the LNG terminal and will offer high reliability and availability of more than 98 %. The core equipment for the new gas-based power plant will include three 9.6 MW gensets, based on the 20-cylinder Rolls-Royce Bergen B35:40 gas engines. These medium-speed gas engines are characterized by high availability and low operating costs. The engine’s efficient combustion technology, in addition to being fuelled by a clean LNG fuel, also ensures low environmental impact coupled with improved performance.

Bergen gas engines
29 MW gas-based power plant for an Indian LNG terminal.

The point of view of Dhamra, LNG CEO

Dhamra LNG CEO, Mr. S.P.Singh, said: «We are delighted to have a Rolls-Royce company supplying us with the critical power system for our upcoming terminal in Odisha.  Rolls-Royce’s selection followed a thoroughly competitive tendering process and we are reassured by their extensive experience in the area of power systems both globally and for Indian LNG terminals.» When commissioned in the end of 2021, the Dhamra LNG Terminal will be the second LNG plant in India that is powered by Rolls-Royce Bergen medium speed engines. Rolls-Royce has earlier supplied and commissioned a 28 MW power plant in 2018, running on LNG fuel to the Indian Oil Corporation LNG Terminal at Ennore, Tamil Nadu. 

Designed for an initial capacity of 5 million tonnes per annum (MTPA), expandable up to 10 MTPA, the proposed Dhamra LNG import and regasification terminal will initially have two full containment type tanks of 180,000 m3 capacity each. Rolls-Royce will be managing the engineering, procurement, and construction of the new gas power plant for the LNG terminal. Rolls-Royce has been a pioneer in the development of the modern lean-burn gas engine concept. With a robust design and proven reliability record, these gas engines have been successfully installed globally across industries. With thousands of installations globally, Rolls-Royce is trusted to deliver complete power solutions to a variety of applications, such as utilities, independent power producers, healthcare, mining sites, greenhouses, hotels, data centres and manufacturing facilities. Rolls-Royce medium-speed generating sets are manufactured by the subsidiary Bergen Engines in Norway.

Highlights

Dellorto two-track strategy

The two-track strategy allows the Dellorto group to extend and customise its expertise in EGR, throttle bodies, power units, BMS and batteries from motorbikes to off-highway applications with long-life requirements

Related articles

MAN ES, 24 dual-fuel engines commissioned by Karpowership

Karpowership – the builder, operator and owner of power-plant ships (Powerships) – has commissioned MAN Energy Solutions to deliver 24 × 18V51/60DF dual-fuel engines. The engines – each providing a capacity of 20.7 MW for power generation – will be employed aboard several barges due to operate globa...